Week of June 29, 2026
Phase: Grading & Infrastructure
Grading activities continued this week, focusing on the ongoing installation of the new storm drain within Carter Avenue within the project site. Installation of the new wet utilities is approximately 80% complete and will continue for several more weeks.
Seasonal weed abatement and brush management work is underway. Crews started on the north side of the property adjacent to the retreat center and are working south. Crews anticipate completing all work by the end of next week.
Air quality monitoring, street sweeping, and dust control measures are ongoing. No air quality exceedances have been reported.
Offsite improvements along Carter Avenue are expected to begin by the end of July. Additional public notification will occur before construction begins.
Week of June 22, 2026
Phase: Grading & Infrastructure
Work over the past two weeks focused on installing wet utilities. New sewer infrastructure has been fully installed throughout the site, and an inspection is scheduled for 6/25. The temporary sewer line should be removed by 7/2. The new stormdrain is fully installed along the extension of Carter Avenue into the project site and work is beginning this week on the internal streets. The installation of new water main will commence after the stormdrain work is completed.
Dust control measures, continuous air quality monitoring, and twice-weekly street sweeping have continued. AQMD inspectors visited the site on 6/12 and found no violations.
Offsite improvements to Carter Avenue are anticipated to commence in the next six to eight weeks, slightly later than originally expected. Carter Avenue and Sunnyside Avenue will be paved upon completion of the onsite utility work. Paving is expected to occur in the fall.
Week of June 15, 2026
Phase: Grading & Infrastructure
Onsite sewer work is now approximately 95% complete. Crews are now beginning to install the new onsite stormdrain system. Stormdrain construction is anticipated to occur over the next three weeks and will be the primary construction activity during this time. The water quality treatment system in the new public park is fully constructed, and the park area has been backfilled.
Dust control measures and air quality monitoring are ongoing. No air quality exceedances were issued this past week. Street sweeping is ongoing on Mondays and Wednesdays.
Week of June 8, 2026
Phase: Grading & Infrastructure
Onsite sewer work is now approximately 95% complete. Crews are now beginning to install the new onsite stormdrain system. Stormdrain construction is anticipated to occur over the next three weeks and will be the primary construction activity during this time. The water quality treatment system in the new public park is fully constructed, and the park area has been backfilled.
Dust control measures and air quality monitoring are ongoing. No air quality exceedances were issued this past week. Street sweeping is ongoing on Mondays and Wednesdays.
Week of June 1, 2026
Phase: Grading & Infrastructure
Construction activities this week have been focused on the installation of new sewer main and laterals. This new infrastructure will be completely installed within the next two weeks. Once the sewer is complete, work on the new stormdrain will commence. Additionally, construction of the new verdura wall systems is complete. Retaining wall construction will begin next week throughout the property. Rough grading is approximately 85% complete. Large grading equipment has been removed from the site. The public will see smaller equipment -- mostly loaders -- moving in and out of the site over the next few weeks.
Dust control measures are ongoing, with water trucks operating during grading activities. Twice weekly street sweeping also continues. Continuous air quality monitoring resulted in no reported exceedances or alerts this week.