Lima Street Water Main Replacement Project
The City is replacing approximately 1,440 linear feet of aging water main on North Lima Street between West Grand View Avenue and West Carter Avenue. The existing infrastructure has reached the end of its service life. Proactively replacing these pipes is necessary to prevent potential water leaks, avoid unplanned service interruptions, and eliminate the increasing maintenance costs associated with outdated lines. This critical upgrade ensures reliable daily water service, improves fire flow reliability for the neighborhood, and supports the long-term sustainability of the City's municipal utility system.
Project Overview
- Location: North Lima Street, from West Grand View Ave to West Carter Ave
- Work Hours: Monday through Friday, 7:00 a.m. to 5:00 p.m.
- Anticipated Duration: Six to eight weeks (including testing, connections, and paving)
- Contractor: AP Engineering (Specification No. WT2601)
Scope of Work
- Installation of 1,440 linear feet of new 6-inch PVC main.
- Connection of 41 new water services.
- Installation of five new fire hydrants and valves.
- Comprehensive pavement restoration and street striping.
Construction Progress (8/6/2026)