Status: Construction
Installation of a new water main along West Carter Avenue between Grove Avenue and Lima Street. The project is part of the City's Water Main Replacement Capital Improvement Program and will improve the reliability and long-term performance of the water distribution system.
October 27, 2026 update: Utility crossings are complete. The next phase requires coordination of water-main work, storm-drain work, and resident access.
| Contractor | La Strada Pipeline, Inc. |
|---|---|
| Construction began | Week of August 24, 2026 |
| Construction contract | $294,070 |
| Project numbers | Tyler Project WT2601 Water Main Replacement Project, CIP No. WS-26001 |