Bailey Canyon Wilderness Park Restoration Project
Status: Field Work Completed
The Bailey Canyon Wilderness Park project used RPOSD RESTORE grant funding for technical assessment, wildfire recovery, drainage and erosion control, vegetation management, restoration, and irrigation improvements. Field work is complete and grant closeout is in progress.
Last updated August 2026.
Grant and Assessment History
Following the January 2025 Eaton Fire, the City received a $200,000 RPOSD RESTORE grant for recovery work at Bailey Canyon and the Mount Wilson Trail. The grant initially assigned $100,000 to each location. After technical evaluation and public review, RPOSD approved a revised allocation of $175,000 for Bailey Canyon and $25,000 for Mount Wilson.
Tetra Tech BAS, Inc. performed shared planning and assessment work for both locations. The work included geotechnical, drainage, erosion, slope stability, structural, mapping, and project planning services. Because the consultant agreement covered both locations, the full Tetra Tech cost should not be assigned solely to Bailey Canyon.
Project Overview
| Location | Bailey Canyon Wilderness Park |
|---|---|
| Fieldwork period | July 2026 |
| Restoration partner | Los Angeles Conservation Corps |
| Irrigation contractor | Mariposa Landscapes, Inc. |
| Closeout status | Final cost and administrative closeout pending confirmation |
Restoration and Drainage Work
The Los Angeles Conservation Corps performed targeted vegetation and weed abatement, constructed naturalized bioswales and drainage channels, trimmed trees, placed rock and boulders, and completed mobilization and site cleanup.
- Removal of invasive vegetation within 15,392 square feet, plus 2,983 linear feet of removal documented during the first week.
- Excavation, grading, and installation of approximately 2,072 square feet of bioswales.
- Trimming and pruning of nine trees.
- Rock placement, limited grading and stabilization, cleanup, and related restoration work.
Irrigation Improvements
Mariposa Landscapes installed irrigation improvements under a separate City agreement. The scope included a backflow preventer and pressure regulator, remote-control valves and controller improvements, quick couplers, hose bibs, elevated rotor heads, trenching, irrigation lines, and related installation work.
RPOSD Grant Allocation
| Grant Project | Cost Category | Revised Allocation |
|---|---|---|
| Bailey Trails Restoration, R76B25 | Soft costs for assessment and project readiness | $25,000.00 |
| Bailey Trails Restoration, R76B25 | Hard costs for wildfire recovery implementation | $150,000.00 |
| Mount Wilson Trails Restoration, R76A25 | Soft costs for completed assessment and project readiness | $25,000.00 |
| Total RPOSD RESTORE grant | $200,000.00 | |
The revised Bailey Canyon allocation is $175,000. The Mount Wilson project retained $25,000 for its completed assessment work. These grant allocations are funding categories, not amounts to add to the vendor agreements below.
Project Costs and Commitments
| Organization | Cost Type and Scope | Amount | How to Read This Amount |
|---|---|---|---|
| Tetra Tech BAS, Inc. | Shared soft costs for Bailey Canyon and Mount Wilson assessment and planning | $44,630.00 paid | Tetra Tech provided assessment and planning services for both Bailey Canyon and Mount Wilson Trail under one agreement. The agreement amount is therefore shown as a shared cost, rather than as a Bailey Canyon-only cost. |
| Los Angeles Conservation Corps | Bailey Canyon vegetation removal, bioswales, drainage, tree trimming, and restoration | $70,820.20 authorized | Bailey Canyon implementation agreement supported by the hard-cost allocation. |
| Mariposa Landscapes, Inc. | Bailey Canyon irrigation improvements | $62,785.00 authorized | Bailey Canyon implementation agreement supported by the hard-cost allocation. |
The two Bailey Canyon implementation agreements total $133,605.20 in authorized commitments. That subtotal is not the final Bailey Canyon project cost. The shared Tetra Tech amount is shown separately to avoid assigning Mount Wilson work to Bailey Canyon or counting grant funding twice. Final paid Bailey Canyon costs will be reported after reimbursement and administrative closeout are complete.
Project Photo Timeline
The photo timeline separates existing conditions from active work and completed improvements. Swipe or scroll horizontally within each stage to view the photographs. This keeps the page compact while preserving the full project record.
1. Before Restoration
2. Restoration Work in Progress
3. Completed Improvements, Irrigation, and Stewardship